Surface Transportation Program Projects

Null

About the Project

 The Mingo intersections 111th, 121st and 131st were all funded in the 2011 bond package which provided matching dollars (25%) for federal construction grant dollars (75%). The intersections are being constructed in the order that the right of way acquisition has been obtained, thus 111th and Mingo was the first project completed. The matching dollars will yield around $3 million in total of federal funds that do not have to burden Bixby taxpayers.

111 Street South and South Mingo Road

This part of the project was started in the winter of 2016 and is already completed. 

121 Street South and South Mingo Road

This part of the project is pending due to Right of Way aspects. 

131 Street South and South Mingo Road

This part of the project is scheduled to start in June of 2019 and scheduled to be completed in the Summer of 2020. 

ODOT opened bids on April 18th for the 131st and Mingo Signalization Project. The Transportation Commission awarded a  $1,439,272.30 contract to Tri-Star Construction Arkansas, LLC  on May 6, 2019. The contract time is 180 days with a planned start time in mid-June.